On the future 270 m long bridge over the Formin HPP canal, seven segments have now been completed on the right intermediate support. Concreting is being carried out progressively from the column in both directions in a symmetrical sequence an in sections of 5.0 m (the first two of 4.0 m), using a pair of cantilever construction trolleys that support the formwork, reinforcement, and freshly placed concrete. The remaining three segments will follow soon, and then construction of the remaining part of the end span to abutment, which is being constructed using the traditional cast-in-situ method of construction and then the joining of both sides of the canal by concreting the closure segment. The bridge, which spans a canal with a water depth of 8 to 14 m, is being built using balanced cantilever construction technology with spans of 77.5 m + 114 m + 77.5 m.On the left intermediate support of the bridge, all ten segments of the cantilever construction have already been completed. Work is now underway on the remaining part of the left end span, which is being constructed using the traditional cast-in-situ method of construction.The construction of the main two-lane road from Markovci to Ormož has been underway since August 2024. On the 16.09 km long section, in addition to the bridge over the Formin HPP canal, Ponting Bridges also designed the already completed, 195 m long Sejanca viaduct and the 83 m long Ormož overpass. The new section will significantly improve the transport system in the Podravska region and traffic safety.
The construction of the already completed Sejanca viaduct was suspended in 2009 due to the economic crisis and the collapse of the main contractor. Due to changed conditions and the reconstruction of the railway line, it was necessary to change the primary design of the viaduct. Designed by Ponting, the viaduct was built in 2020 and competed in 2025, enabling the construction site traffic and the delivery of bulk material from the Sejanca viaduct to the Formin hydroelectric power plant canal.
The contractor of the works is a consortium of companies Pomgrad, VOC Celje and Cestno podjetje Ptuj, the investor is the Motorway Company of the Republic of Slovenia (DARS), and the engineer is DRI Ljubljana. The section is expected to be completed in early 2027.
Project details:
Bridge over HPP Formin canal